Unit G9

Click photo to enlarge/view gallery

Full design and construction of an individual extension to an existing warehouse and distribution centre.  Redesigned by Triton and our designers, Michael Denton Associates, this involved rotating the building and changing the roof pitch orientation and installation of additional roof braces, which increased the storage capacity of the building.  This was done without opening up existing roof structure to minimize disruption to the client's existing operations, and to save the client money.  All of the works were completed in only 12 weeks, four weeks ahead of schedule.

Created by Floyd